Which part of the ABCD risk management model is specifically tied to making risk decisions?

Prepare for the Navy Operational Risk Management Test. Hone your skills with comprehensive multiple choice questions and insightful explanations. Elevate your readiness with targeted study materials!

In the context of the ABCD risk management model, the part that is specifically tied to making risk decisions is known as "Balance Resources." This component involves evaluating the identified risks against the resources available to manage those risks effectively. It is during this balancing act where decision-makers determine whether the risks are acceptable, whether to implement control measures, or whether further action is necessary.

The emphasis on balancing resources is crucial because it involves assessing the potential impact of risk against the capability of the team or organization to mitigate that risk. This decision-making process ensures that resources are allocated in a way that best addresses the identified risks while maximizing efficiency and safety.

The other components of the model, while important in their own right, serve different purposes within the overall risk management framework. For instance, assessing resources focuses on identifying and quantifying the available assets that can be used to manage risks, while communicating concerns is about sharing information to ensure all stakeholders understand the risk landscape. Controlling hazards deals with implementing measures to reduce or eliminate potential hazards once they have been identified. Each of these aspects plays a fundamental role in ORM, but the key to decision-making specifically lies within the balancing of resources.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy